Black background with Flinders logo and yellow text underneath saying, Improving Our Space

Sturt Gym Strength Lab Upgrades

From Tuesday 11 June, there will be no access to the Sturt Gym and rooms G119, G120 and S101a as the following works commence:

  • Demolition of walls to increase room size.
  • New flooring.
  • Updated audio-visual teaching aids in Sturt Gym.
  • Updated gym equipment and air conditioning.
  • Changed egress through the rear (western) door.

These works are expected to be completed in August.

Team moves in PSB and Registry

Due to refurbishment works in the Professional Services Building (PSB) and Registry building, you will find several teams operating in interim homes. These works will be completed later in the year.

Team Where are they now? Where will they end up?
Alumni and Advancement

 

Registry rooms 205, 216 and 217 Registry rooms 203, 205, 216 and 217
Business Intelligence and Planning Registry room 121 Registry rooms 212 and 218
Government and External Relations PSB level 2 Registry room 223
Governance, Legal and Risk Move complete – PSB level 2
International Services team Move complete – Registry room 117 and PSB level 1
Media and Communications Registry rooms 210 and 223 On 20 June, moving back into

Registry rooms 200, 201

201A, 202

People and Culture Staying in Registry room 030 until end August – then moving to Registry rooms 124-130 Back to Registry room 030

 

Work, Health and Safety Formerly PSB level 2. Now on Level 1 Registry rooms 124-130 (where Governance, Legal and Risk used to be.) To Registry room 030

Improvement projects in CSE buildings and car park 7 ongoing through May 

The new ground floor undergraduate science lab redevelopment works are progressing well – as is the roof renewal/stormwater upgrade in and around Physical Sciences and car park 7. If you work in CSE buildings, check out the updates on the CSE Central SharePoint page. Visitors to the area, please note the compound and barriers may change and/or move around Anchor Court, so follow directions on signage and allow extra time to take detours.

Car Parks 2 and 3 EV Charging Bay Maintenance

From 6.30am until noon on Wednesday 5 June, the 15 ‘blue variable rate’ EV chargers spread across car parks 2 and 3 (the bays with green painted signs on the road surface) will be out of action as they undergo planned maintenance. They will not be available for use during this time. Please refrain from charging your EV until the afternoon on June 5, or charge it in car parks 6, 9 or 14 (Sturt). Note that there are time limits for charging an EV (including 2 hours in car park 6). Please refer to the parking webpage for full details.

Advance notice of July electrical maintenance works

Power outages are scheduled on weekends in July for essential electrical maintenance works across South Ridge buildings and the Education building. To minimise disruption to teaching and learning, we are combining maintenance works with the installation of a new transformer for the Biology building in the July mid-semester break.

Who is affected and when? 

• All South Ridge buildings – over the weekends of 6-7 July and 13-14 July.

• Education building at North Ridge on 21 July.

Details in coming weeks will explain signage in the area, emails and on college-specific communication channels. View the full electrical maintenance schedule here.